NATIONAL ASSOCIATION OF G.R.
No. 163935
ELECTRICITY CONSUMERS FOR
REFORMS (NASECORE),
represented Present:
by PETRONILO ILAGAN,
FEDERATION OF VILLAGE PANGANIBAN, C.J.,
ASSOCIATIONS (FOVA),
represented PUNO,
by SIEGFRIEDO VELOSO, and QUISUMBING,
FEDERATION OF LAS PIÑAS YNARES-SANTIAGO,
HOMEOWNERS ASSOCIATIONS SANDOVAL-GUTIERREZ,
(FOLPHA), represented
by CARPIO,
Petitioners, CORONA,*
CARPIO-MORALES,
CALLEJO, SR., AZCUNA,**
- versus - TINGA,
CHICO-NAZARIO,
GARCIA,
and
VELASCO,
JR., JJ.
ENERGY
REGULATORY
COMMISSION
(ERC) and MANILA Promulgated:
ELECTRIC
COMPANY (MERALCO),
Respondents.
August 16, 2006
x- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - x
CALLEJO, SR., J.:
The Energy Regulatory Commission (ERC) and the
Manila Electric Company (MERALCO), in their respective motions, seek
reconsideration of the Court’s Decision[2]
dated P3.1886 per kilowatt hour (kWh) to P3.3213 per kWh.
The Private Electric Power Operators Association, Inc. (PEPOA) filed its Motion for Leave to Intervene and to Admit Attached Comment-in-Intervention and the said Comment-in-Intervention. The Philippine Independent Power Producers Association (PIPPA), without seeking leave of Court, filed its Intervention.
In the Decision, the Court essentially held that, in issuing the assailed Order, the ERC committed grave abuse of discretion, thus:
(1) MERALCO’s amended application for
the increase of its generation charge was not published in a newspaper of
general circulation in violation of Section 4(e), Rule 3 of the Implementing
Rules and Regulations (IRR) of Republic Act No. 9136, otherwise known as the
Electric Power Industry Reform Act of 2001 (EPIRA);
(2) The Generation Rate Adjustment
Mechanism (GRAM) Implementing Rules promulgated by the ERC on February 24,
2003, which was relied upon by the ERC and MERALCO as basis for the approval of
the latter’s amended application for the increase of generation charge and
which does not require such publication, was likewise not published in the
Official Gazette or in a newspaper of general circulation. Further, the GRAM Implementing Rules was not
filed with the Office of the National Administrative Register (ONAR). This lack of publication of the GRAM
Implementing Rules violates the fundamental principle of due process as
enunciated by the Court in the landmark case of Tañada v. Tuvera.[3]
According to the Court, Section 4(e),
Rule 3 of the IRR of the EPIRA speaks of “any application or petition for rate
adjustment or any relief affecting the consumers.” The said provision does not make any
distinction; hence, any application or petition that would result in the
adjustment or change in the retail rate or total price paid by the end-users,
whether such is occasioned by the adjustment or change in the charges for
generation, transmission, distribution, supply, etc., falls within its
contemplation. MERALCO’s amended
application for the increase of its generation charge is thus properly covered
by Section 4(e), Rule 3 of the IRR of the EPIRA and its lack of publication,
which constitutes non-compliance therewith, is fatal.
The Court held that the ERC and
MERALCO’s reliance on the GRAM Implementing Rules is unavailing. To recall, ERC and MERALCO argued that the
latter’s amended application for the increase of its generation charge is not
covered by Section 4(e), Rule 3 of the IRR of the EPIRA but, instead, is governed
by the GRAM Implementing Rules. The
latter does not contain the requirement of publication of any application filed
thereunder. However, as found by the
Court, the GRAM Implementing Rules was not published in the Official Gazette or
in any newspaper of general circulation in violation of the fundamental
principle of due process. Consequently,
the GRAM Implementing Rules has no force and effect for it is axiomatic that
“publication in the Official Gazette or a newspaper of general circulation is a
condition sine qua non before
statutes, rules or regulations can take effect.”[4]
The ERC submits the following grounds
in support of its Motion for Reconsideration:
The Honorable Court erred in ruling that “Section 4(e), Rule 3 of the IRR of the EPIRA speaks of ‘any application or petition for rate adjustment’ without making any distinctions” despite the fact that the framers thereof intended it to apply to a general rate proceeding and not to filings or applications made pursuant to adjustment clauses or what are referred to as “escalator clauses”.
The Honorable Court erred in ruling that “the amended application of respondent MERALCO for the increase of its general [should read generation] charge is covered by Section 4(e), Rule 3 of the IRR of the EPIRA” notwithstanding that ERC Case No. 2004-112 wherein the June 2, 2004 Order of respondent ERC was issued is not a general rate proceeding but one instituted pursuant to the Generation Rate Adjustment Mechanism (GRAM) which the ERC adopted to improve on the then existing adjustment mechanism known as the Purchased Power Adjustment (PPA) and the resultant nullification by the Honorable Court of the June 2, 2004 Order of the ERC and its declaration that the GRAM Guidelines had not become effective, prejudiced the interests of the consumers.
The Honorable Court erred in
giving Section 4(e) of Rule 3 of the EPIRA IRR an expansive coverage by making
it apply to any or all applications/petitions filed with respondent ERC that
would result to [sic] changes in electricity rates the result of which would
paralyze the ERC and render it unable to discharge its mandate under the EPIRA
and in this sense, said IRR effectively contravenes and defeats the very law it
seeks to implement.[5]
For its part, MERALCO proffers the following grounds in support of its Motion for Reconsideration:
IT COULD NOT HAVE BEEN THE
INTENT OF THE IRR TO COVER AUTOMATIC ADJUSTMENT CLAUSES.
THE APPLICATION OF RULE 3,
SECTION 4(E) OF THE EPIRA IRR TO GRAM WOULD RESULT IN ABSURDITY AND UNDERMINE
THE FINANCIAL VIABILITY OF THE DISTRIBUTION UTILITIES AS PROTECTED BY EPIRA.
THE IMPLEMENTATION OF THE
DECISION OF THE HONORABLE COURT DATED 02 FEBRUARY 2006 WOULD RESULT IN SEVERE
REPERCUSSIONS TO THE ENTIRE ELECTRIC INDUSTRY AND TO THE PUBLIC IN GENERAL, A
SITUATION WHICH COULD NOT HAVE BEEN CONTEMPLATED BY THE FRAMERS OF THE LAW AND
THE EPIRA IRR.
PRIVATE RESPONDENT MERALCO,
ALONG WITH THE OTHER DISTRIBUTION UTILITIES AND THE NPC ACTED IN GOOD FAITH IN
RELYING UPON THE RULES AND REGULATIONS ISSUED BY THE ERC; HENCE, THE
NULLIFICATION OF THE GRAM RULES MUST BE APPLIED PROSPECTIVELY SO AS NOT TO
UNDULY PREJUDICE THE UTILITIES.[6]
The
arguments raised in the respective motions of the ERC and MERALCO, as they are
substantially similar, shall be addressed jointly. On
the other
hand, the arguments raised by the intervenors are basically ancillary to those
of the ERC and MERALCO; hence, the Court finds no need to address them
separately.
The ERC and
MERALCO mainly posit that MERALCO’s amended application for the increase of its
generation charge is not covered by Section 4(e), Rule 3 of the IRR of the
EPIRA. For clarity, the provision is
quoted anew:
(e) Any application or petition for rate adjustment or for any relief affecting the consumers must be verified, and accompanied with an acknowledgement receipt of a copy thereof by the LGU Legislative Body of the locality where the applicant or petitioner principally operates together with the certification of the notice of publication thereof in a newspaper of general circulation in the same locality.
The ERC may grant provisionally or deny the relief
prayed for not later than seventy-five (75) calendar days from the filing of
the application or petition, based on the same and the supporting documents
attached thereto and such comments or pleadings the consumers or the LGU
concerned may have filed within thirty (30) calendar days from receipt of a
copy of the application or petition or from the publication thereof as the case
may be.
Thereafter, the ERC shall conduct a
formal hearing on the application or petition, giving proper notices to all
parties concerned, with at least one public hearing in the affected locality,
and shall decide the matter on the merits not later than twelve (12) months
from the issuance of the aforementioned provisional order.
This Section 4(e) shall not apply to
those applications or petitions already filed as of
In Freedom from Debt Coalition v. ERC,[7]
the Court outlined the procedure enjoined by the above provisions, thus:
(1) The applicant must file with the ERC a verified
application/petition for rate adjustment.
It must indicate that a copy thereof was received by the legislative
body of the LGU concerned. It must also
include a certification of the notice of publication thereof in a newspaper of
general circulation in the same locality.
(2)
Within 30 days from receipt of the application/petition or the
publication thereof, any consumer affected by the proposed rate adjustment or
the LGU concerned may file its comment on the application/petition, as well as
on the motion for provisional rate adjustment.
(3)
If such comment is filed, the ERC must consider it in its action on the
motion for provisional rate adjustment, together with the documents submitted
by the applicant in support of its application/petition. If no such comment is filed within the 30-day
period, then and only then may the ERC resolve the motion for provisional rate
adjustment on the basis of the documents submitted by the applicant.
(4)
However, the ERC need not conduct a hearing on the motion for
provisional rate adjustment. It is
sufficient that it consider the written comment, if there is any.
(5) The ERC must resolve the motion for provisional rate adjustment within 75 days from the filing of the application/petition.
(6) Thereafter, the ERC must conduct a full-blown hearing on the application/petition not later than 30 days from the date of issuance of the provisional order and must resolve the application/petition not later than 12 months from the issuance of the provisional order. Effectively, this provision limits the lifetime of the provisional order to only 12 months.[8]
The Court stressed
in Freedom from Debt Coalition two
important new requirements prescribed by Section 4(e), Rule 3 of the EPIRA IRR:
“first, the need to publish the application in a newspaper of general
circulation in the locality where the applicant operates; and second, the need
for the ERC to consider the comments or pleadings of the customers and the LGU
concerned in its action on the application or motion for provisional rate
adjustment.”[9]
In their
respective motions for reconsideration, the ERC and MERALCO vigorously contend
that Section 4(e), Rule 3 of the IRR of the EPIRA applies only to a general
rate application of a distribution utility and not to its application for cost
recovery pursuant to “escalator clauses” or “purchased power or fuel adjustment
clauses.” Since MERALCO’s amended
application is for the increase of its generation charge and, as such, entails
a cost recovery adjustment, then it is not covered by Section 4(e), Rule 3 of
the EPIRA IRR. Specifically, MERALCO’s
amended application for the increase of its generation charge allegedly does
not need to be published and the ERC is not required to consider the customers’
comments thereon and conduct the necessary hearing.
The ERC and
MERALCO point out that by its nature, an application for cost recovery pursuant
to “purchased power or fuel adjustment clauses” or “escalator clauses” requires
a summary proceeding to allow a utility to update certain costs such as fuel
and/or generation costs. To require the
ERC to approve applications of this nature only after notice and hearing would
allegedly go against the precise and very purpose for which automatic cost
updating/adjustment mechanisms are instituted, i.e., to have an effective mechanism to reflect actual costs of
power and to have a timely adjustment, upwards or downwards, for the interest
of all parties concerned. The matter is
allegedly mechanical and merely one of computation.
The ERC and MERALCO rely heavily on American case law explaining the nature of these “escalator clauses” or “purchased power or fuel adjustment clauses,” thus:
“An escalator clause is a
method designed to enable a utility to adjust its revenues either upward or
downward to reflect changing elements of operating costs of a public utility
without having to resort to the cumbersome procedure of filing a new rate case
as often as material changes on the factors effecting the reasonableness of the
rates occur (Duquesne Light Co. v. Pennsylvania Public Comm., 5 PUR 3d,
141-142).
An escalator clause serves
equitable and procedural purposes. The
use of such method guarantees to the customer that he is not charged more than
he ought to pay and to the utility that it gets its due compensation for its
services. The method helps unclog the docket of the utility commissions and the
courts especially in times of rapid fluctuations in prices (Re Lynchburg Gas
Co., 6 PUR 3d., 34; City of Norfolk v. Virginia Electric and Power Co., 11 PUR
438).” (Camilo D. Quiason, Annotation on Rate Making, 41 SCRA 701).
The power adjustment clause
is the most convenient regulatory mechanism that addresses the need of the
distribution utilities to recover their cost of power purchased in the most
expeditious manner. It differs from an
ordinary application for adjustment of rates of the distribution utilities in that the former is a summary
proceeding designed solely to allow a utility to update certain costs such as
fuel and/or generation costs. (Re
Indianapolis Power & Light Co., 1984, 62 PUR 4th ed. 666)
The use of the power
adjustment clause is common and has, in fact, received widespread recognition
and approval in international jurisdiction. In the
In
In this respect,
Commissioner Hooker of
“The Commission has for many
years approved rates for lower costs of electric power that are based on fuel
clauses. The operation of those clauses results in increases or decreases in
rates as the cost of fuel increases or decreases. No objection has ever been
made to such rates despite the long period of their effectiveness. They cannot be distinguished in effect from
the escalator provision proposed here.
Electric rates with fuel clauses were considered and accepted by this
commission more than thirty years ago … (citing
in Re Virginia R. & Power Co. PUR 1921C 193, 208; Re Lynchburg Traction
& Light Co. PUR 1921E 87).”
Commissioner Hooker further
said:
“The legality and propriety of such clauses
were considered in length in 1953 by the New York Public Service Commission in
a proceeding covering the large gas distributors in the
The New York Public Service
Commission sustained the legality and propriety of adjustment clauses [Re Brooklyn Borough Gas Co. (NY 1953) 100
PUR NS 271]. Likewise, the Edison
Electric Institute estimated that in 1948, over 85% of all private power
companies had adjustment clauses for electric energy sold to industrial
customers. Subsequently, such clauses have also spread to rates for commercial
service. The trend continued toward the use of adjustment clauses for fuel also
for residential type of utility rates (Welch,
Preparing for the Utility Rate Case, 1954 ed., 234; 50 Public Utilities
Fortnightly, No. 9, p. 637, 1952, 54 Public Utilities Fortnightly, No. 4, 217,
1955)
In February 1948, a fuel
adjustment clause became effective in the electric rate schedules of
Pennsylvania Power & Light Company, of general application for certain
commercial and industrial users. In
April 1948, the commissions of North and
The Court is not
quite impressed with the foregoing case law relied upon by the ERC and MERALCO
because, in fact, they do not entirely support ERC’s
and MERALCO’s theory that mechanisms for recovery of
purchased power or fuel costs are necessarily “automatic.” As will be shown shortly, automatic
adjustments in rates according to a fixed formula, without the necessity for
proceedings or hearings by the public utilities commission whenever specified
costs of the utilities change by a certain amount, while permissible under some
statutes in the United States, is improper under others. Even some of the cases
cited by the ERC and MERALCO illustrate that mechanisms for the recovery of
purchased power or fuel costs are not necessarily antithetical to the
requirements of notice and hearing. For
example, in Re
On
Pursuant to notice published as
required by law, proof of which was incorporated into the record and placed in
the official files of the commission, a public hearing in this cause was
held on October 9, 1984, at
The commission, based upon the
applicable law and all evidence of record herein, and being duly advised in the
premises, now finds as follows:
1.
Notice and Commission Jurisdiction.
Due legal and timely notice of the commencement of the public hearing in
this cause was given and published by the commission as required by law. IPL operates a public electric utility and as
such, is subject to the jurisdiction of this commission as provided for in the
Public Service Commission Act, as amended, and the provisions of that act
authorize the commission to act in this proceeding. Accordingly, the commission has jurisdiction
over the parties and the subject matter herein.
x
x x
In Re Arizona Public Service Company,[12]
the following discussion on the history of Purchased Power and Fuel Adjustment
Clause (PPFAC) again belies the ERC’s and MERALCO’s
claim that “purchased power and fuel adjustment clauses” are “automatic” and,
therefore, no hearings can be conducted with respect to applications for
adjustments of this kind:
Arizona Public Service Company (APS) has utilized a form of PPFAC since its origins in the early 1950’s. See Decision No. 26996 (December 29, 1952). At first, the PPFAC only applied to gas generation. The provision was expanded to other fuels (but not purchased power) in Decision No. 33813 (April 3, 1962), and the adjustment was calculated on a plant-by-plant basis. This procedure was abandoned by Decision No. 44262 (June 14, 1974). The PPFAC was calculated on a system-wide basis, and the tremendous growth in interchange sales required incorporation of purchased power for the first time. Decision No. 44262 (which immediately followed the oil embargo) allowed for automatic monthly adjustments with no prior Commission review. Decision No. 46513 (October 30, 1975) created monthly reporting requirements and excluded fuel handling costs and line losses from the PPFAC. However, the PPFAC’s basic structure remained intact.
On
x x x
The
Illinois Public Utilities Commission and Indiana Public Service Commission had
been reported to require hearings before any
increase in rates was approved, even if the request for such increase was based
on the increase in the prices of coal:
A few statutes, however, require that a public hearing be held before any increase in rates is approved. The Illinois Public Utilities Commission, interpreting a statutory provision that “no public utility shall increase any rate ... under any circumstances whatsoever, except upon a showing before the Commission and a finding by the Commission that such increase is justified,” held:
“This seems to contemplate a formal
showing which would justify any increase allowed, and certainly does not
contemplate the allowance of an increase of rates predicated on the bare
statement of the public utility involved that it has paid a certain amount for
coal.”
The
Indiana Public Service Commission reached the same conclusion, although the
statute involved did not specifically require a hearing.
“[I]t would appear that the Commission is
without power to confer authority for increasing rates contingent upon some
future happening, and that it would be necessary for the Commission to
determine whether or not the price of coal had increased or decreased. Therefore it makes little difference whether
the coal clauses are placed in the tariff or not, for the reason that it would
be necessary for the Commission, either on petition of the consumer or the utility,
to ascertain the prevailing price of coal before allowing an increase or
reduction in rates, on the theory that no increase in rates can be allowed
without a public hearing.”[13]
On the
other hand, in State ex rel. Utility
Consumers Council of Missouri, Inc. v. Public Service Commission,[14]
the Supreme Court of Missouri disallowed the use of automatic fuel adjustment
clause as part of residential rate structure for lack of statutory authority.[15] Objections to the use of fuel adjustment
clause were noted in the said case in this wise:
Numerous objections have been raised to
the use of fuel adjustment clauses. Even
those states which approve them have required numerous safeguards surrounding
their use, as has the commission in this case.
The principal objections have been that to permit such automatic
adjustments would be an abdication of the commission’s rate making function;
that it would violate the spirit and purpose of regulatory law; that it allows
an increase in rates without consideration of all factors, thus overweighing
the effect of one factor, and ignoring compensating economies; that it shifts
the burden of proving reasonableness or unreasonableness from the utility to
the consumer; that it violates the principle that utility rates should be
definite and published in order to insure stability and notice of rates to
consumers and in order that consumers understand their rates and thus have the
knowledge necessary to determine if complaint is warranted; that utilities
would lose any incentive to keep down fuel costs where they know such costs can
be fully and automatically passed on to the consumer; and that presence of a
fuel adjustment clause may bias selection of fuels or production methods so
that the utility will choose the method which allows it to pass on the most
cost and is thus cheapest to it, rather than the method which is cheapest to
all.[16]
The
following ratiocination made by the Missouri Supreme Court in State ex rel. Utility Consumers Council of
Missouri, Inc. is likewise relevant to the present case:
x x x
While fuel costs are to a large extent dependent on general market
conditions and periodically fixed contract costs, the utility does exercise
control over its fuel costs when it negotiates its fuel contracts or chooses
what fuel to buy or burn in what generating unit. It also is possible to offset fuel costs with
savings from efficiencies in other areas of operation, such as salaries, wages,
taxes, depreciation and materials and supplies other than fuel. This, of course, does not necessarily mean
that a fuel adjustment clause is not authorized by statute, but it does mean
that it is not authorized as simply an extension of the reasoning in Hotel
Continental. We must now determine whether it is otherwise authorized by
statute.
Respondents themselves have difficulty
pointing to what provisions in the statutes give them authority to utilize a
fuel adjustment clause. In their brief,
as noted Supra, they simply argue that “it is clear that the statutes and case
law in
It is for the legislature, not the PSC,
to set the extent of the latter’s jurisdiction.
The mere fact that the commission has approved similar clauses in the
past, or that other states permit them, is irrelevant if they are not permitted
under our statute.[20]
In the same
manner, the mere fact that certain jurisdictions in the
Indeed, the
Court’s determination of the nullity of the ERC Order dated
The publication and comment requirements in Section 4(e), Rule 3 of the IRR of the EPIRA were held to be in keeping with the foregoing avowed policies of the EPIRA. The pertinent disquisition in Freedom from Debt Coalition is quoted anew:
Obviously, the new requirements are aimed at protecting the consumers and diminishing the disparity or imbalance between the utility and the consumers. The publication requirement gives them enhanced opportunity to consciously weigh the application in terms of the additional financial burden which the proposed rate increase entails and the basis for the application. With the publication of the application itself, the consumers would right from the start be equipped with the needed information to determine for themselves whether to contest the application or not and if they so decide, to take the needed further steps to repulse the application. On the other hand, the imposition on the ERC to consider the comments of the customers and the LGUs concerned extends the comforting assurance that their interests will be taken account. Indeed, the requirements address the right of the consuming public to due process and at the same time advance the cause of people empowerment which is also a policy goal of the EPIRA along with consumer protection.[22]
Clearly, viewed in light of the EPIRA, its IRR and its policy objectives, the ERC’s and MERALCO’s contention that the latter’s amended application for the increase of generation charge is not covered by Section 4(e), Rule 3 of the IRR cannot be sustained. For to allow MERALCO or any distribution utility to increase its generation charge without publication of its application therefor and to allow the ERC to approve the same without taking into consideration the comments thereon of the consumers and the LGUs concerned, on the ground that it is a cost recovery adjustment, would be to erode the EPIRA’s avowed policies of people empowerment and consumer protection. Significantly, Section 75 of the EPIRA enjoins that it (the EPIRA) shall be construed “in favor of the establishment, promotion, preservation of competition and people empowerment so that the widest participation of the people, whether directly or indirectly, is ensured.”
The ERC and MERALCO attempt to take the latter’s amended application for the increase of its generation charge out of the coverage of Section 4(e), Rule 3 of the IRR of the EPIRA by arguing that it is not in itself a rate. This attempt is futile because, as already pointed out in the Decision, the approval of the same would effectively increase the rates payable by the consumers. Accordingly, such application is within the contemplation of Section 4(e), Rule 3 of the EPIRA IRR as it covers “any application or petition for rate adjustment or any relief affecting the consumers.”
It bears reiterating that the ERC is not precluded from promulgating rules, guidelines or methodology, such as the GRAM, for the recovery by the distribution utilities of their fuel and purchased power costs. However, these rules, guidelines or methodology so adopted should conform to requirements of pertinent laws, including Section 4(e), Rule 3 of the IRR of the EPIRA.
For example, the ERC may adopt a summary or abbreviated hearing with respect to the distribution utilities’ applications to recover their purchased power or fuel adjustment costs but, and this should be stressed, the requirements of publication of the application as well as that the consumers and the local government units concerned be given 30 days from such publication to submit their comments thereon shall not be dispensed with. The abbreviated or summary hearing so adopted shall be conducted only after strict compliance with the publication and comment requirements. It should be made clear that, unless Section 4(e), Rule 3 of the IRR of the EPIRA is amended, the adjustments of rates based on purchased power or fuel adjustment costs shall not or in no case be “automatic.”
In any case, as already pointed out, MERALCO’s concern that it would be subjected to a long and tedious process of recovering its purchased power and fuel costs is addressed by the ERC’s power of interim rate regulation as upheld by the Court in Freedom from Debt Coalition. MERALCO’s contention that the ERC’s power to grant provisional relief applies only to general rate applications, and not to applications for adjustments to recover purchased power or fuel costs, is tenuous. On this point, this statement made by the Missouri Supreme Court finds application: “If the electric companies are faced with an ‘emergency’ situation because of rising fuel costs, they can take advantage of the method set up by the legislature to deal with such situations and file for an interim rate increase on the basis of an abbreviated hearing.”[24] As already stated in the Decision, the grant to the ERC of the power of interim rate regulation is precisely for it to “be able to swiftly and flexibly respond to the exigencies of the times,”[25] including rising fuel costs.
The ERC, for its part, has raised the matter of logistical constraints vis-à-vis the requirement in Section 4(e), Rule 3 of the EPIRA IRR of conducting hearings with respect to the distribution utilities’ applications to recover purchased power or fuel costs. Among others, it envisioned a scenario where, in a given year, it would allegedly be required to travel to and conduct 1,680 hearings in various localities all over the country for cost recovery filings alone. It would allegedly take the ERC 4½ years to decide the 1,680 cost recovery filings made in just a year even if it would render decisions on Saturdays and Sundays. By the Court’s declaration that applications of distribution utilities for adjustments to recover their purchased power or fuel adjustment costs are covered by Section 4(e), Rule 3 of the EPIRA IRR, according to the ERC, “it is being required to enforce something that cannot be accomplished, given the insurmountable time, budgetary and other logistical constraints it faces.”[26] In such a case, it would allegedly be impossible for the ERC to attend to its other equally important responsibilities and functions under the EPIRA, i.e., to ensure the successful restructuring of the electric power industry.
These contentions are hardly persuasive. The Court is not unmindful that it would be easier for the ERC to adopt a method, such as the GRAM, to allow distribution utilities to recover their purchased power or fuel costs without need for the ERC to conduct hearings or even to consider the comments of the consumers. This would certainly be less burdensome, more economical and efficacious for the ERC. But it would do well to remind the ERC that the Constitution recognizes higher values than administrative economy, efficiency and efficacy. The Bill of Rights, in general, and the Due Process Clause in particular, were designed to protect the fragile values of a vulnerable citizenry from the overbearing concern for efficiency and efficacy that may characterize praiseworthy government officials.[27] Moreover, when an administrative procedure, such as the GRAM, runs roughshod over fundamental values, like the right of the citizenry to due process, enshrined in the Constitution and other statutes, the Court cannot let such procedure stand.
In this connection, the hearings on applications for rate adjustments, as a component of procedural due process under Section 4(e), Rule 3 of the EPIRA IRR, shall be conducted after compliance with the other procedural due process requirements therein. The ERC need not conduct a hearing in the exercise of its power of interim rate regulation. Nonetheless, the other components of procedural due process, i.e., the publication and comment requirements of the said provision, shall be strictly complied with before the ERC takes action on the application itself or the motion for provisional rate adjustment. Publication of the application for rate adjustments in a newspaper of general circulation in the locality where the applicant operates and the need for the ERC to consider the comments thereon of the consumers and the local government units concerned filed within 30 days from their receipt of a copy of the application or the publication thereof are, therefore, mandatory.
As Justice Dante O. Tinga explained in his concurring opinion: “the publication under the IRR has a dual purpose: first, it is jurisdictional because without it, the ERC would be powerless to assume jurisdiction over the petition; and second, it is a necessary component of procedural due process aimed at giving the petition as wide publicity as possible so that all persons having an interest in the proceedings may be notified thereof.”[28]
By way of recapitulation, the
ERC Order dated
To address MERALCO’s plea
that the present ruling be prospectively applied, it behooves the Court to
clarify that the petition in the present case prayed only for the nullification
of the ERC Order dated P3.1886
to P3.3213 per kWh. The Court,
without overreaching itself, cannot extend the present ruling to the other ERC
orders which have not been brought before it. Hence, the applicability or
non-applicability of the ruling in the present case to the other orders of the
ERC will have to be determined if and when the proper petitions are filed with
the Court.
WHEREFORE, the Motion for Reconsideration dated
The Comment-in-Intervention
dated
Consequently, upon finality
of the Decision dated P0.1327 per kWh (representing the unauthorized increase from P3.1886
to P3.3213 per kWh under the nullified ERC Order dated
SO ORDERED.
ROMEO
J. CALLEJO, SR.
Associate Justice
WE
CONCUR:
ARTEMIO V.
PANGANIBAN
Chief Justice
REYNATO
Associate Justice Associate
Justice
CONSUELO YNARES-SANTIAGO ANGELINA SANDOVAL-GUTIERREZ
Associate Justice
Associate Justice
ANTONIO
T. CARPIO MA. ALICIA
AUSTRIA-MARTINEZ
Associate Justice Associate
Justice
On leave
RENATO C. CORONA CONCHITA
CARPIO MORALES
Associate
Justice Associate
Justice
On official
leave
ADOLFO S. AZCUNA DANTE O. TINGA
Associate
Justice
Associate Justice
MINITA
V. CHICO-NAZARIO CANCIO
C. GARCIA
Associate
Justice Associate Justice
PRESBITERO J. VELASCO, JR.
Associate
Justice
Pursuant to Section 13,
Article VIII of the Constitution, it is hereby certified that the conclusions
in the above Resolution were reached in consultation before the case was
assigned to the writer of the opinion of the Court.
ARTEMIO
V. PANGANIBAN
Chief Justice of the
* On leave.
** On official leave.
[1] Rollo, pp. 741-782.
[3] 230 Phil. 528 (1986).
[4] Republic
of the
[5]
Rollo, pp. 783-784.
[6]
[7] G.R. No. 161113, June 15, 2004, 432 SCRA 157.
[8]
[9]
[10] MERALCO’s Motion for Reconsideration, pp. 9-12; rollo, pp. 846-849.
[11] 62 P.U.R. 4th 666.
[12] 76 P.U.R. 4th 399.
[13] Trigg, Escalator Clauses in Public Utility Rate Schedules, 106 U.Pa.L.Rev. 964.
[14] 585 S.W.2d 41, 33 P.U.R.4th 273.
[15] The Missouri Supreme Court observed that,
prior to the assailed order of the public service commission, the fuel
adjustment clause had never before permitted to become part of a residential
rate schedule in
[16] Supra note 12, at 49-50. Citations omitted.
[17] The said provision provide, in part, that the
public service commission has the power to require all electric companies to
“file with the commission and to print and keep open to public inspection
schedules showing all rates and charges made, established or enforced or to be
charged or enforced, all forms of contract or agreement and all rules and
regulations relating to rates, charges and service used or to be used… No
change shall be made without 30 days notice and 30 days publication except as
authorized by the commission.”
[18] Referring to Hotel Continental v. Burton, 334 S.W.2d 75, where the same state Supreme Court affirmed the public commission’s power in a rate case to permit the Kansas City Power & Light Co. to include in its rate schedule a tax adjustment clause (TAC) which permitted the company to state separately on each customer’s bill a charge equal to any part of a license, occupation or other similar fee or tax applicable to service by the utility to that customer and imposed by local taxing authorities on the basis of gross receipts.
[19] Supra note 12, at 57, citing State ex rel. Laclede Gas Co., 535 S.W. 2d 561.
[20] Supra note 12, at 54. Citations omitted.
[21] Supra note 5, at 195 citing Sec. 2(f), (c) and (e) of the EPIRA.
[22]
[23]
[24] Supra note 17.
[25] Concurring and Dissenting Opinion of Justice Reynato S. Puno in Freedom from Debt Coalition, supra note 5, at 234.
[26] ERC’s Motion for Reconsideration, pp. 17-25; rollo, pp. 799-807.
[27] Stanley,
Sr. v. State of
[28] Supra note 5.